Construction closures Sunday - Thursday on W. Kellogg

July 23, 2010|By Chris Durden | KWCH 12 Eyewitness News

(WICHITA, Kan.) — Road work continues on West Kellogg Sunday through Thursday night.

Driving surface replacement will require overnight closures of interchange ramps at I-235, West and Edwards streets.

The normal work week on this project is Sunday through Thursday, 7 p.m. – 6 a.m.

One lane on Kellogg is closed at 7 p.m. and a second lane at 9 p.m.

Ramps adjacent to work zones are also closed. All lanes and ramps are open to traffic by 6 a.m.

Sunday night:
•    SB I-235 to EB U.S. 54 ramp
•    NB I-235 to EB U.S. 54 ramp
•    EB U.S. 54 to NB I-235 ramp (to be re-opened by 3 a.m.)
•    EB U.S. 54 to West St. ramp (to be closed at 11 p.m.)

Monday night:
•    EB U.S. 54 to SB I-235 ramp      

Tuesday night:

•    WB U.S. 54 to NB I-235 ramp
•    WB U.S. 54 to SB I-235 ramp
•    NB I-235 to WB U.S. 54 ramp

Wednesday night:
•    WB U.S. 54 to West St. ramp
•    SB I-235 to WB U.S. 54 ramp

If the project stays on schedule, work could move to
I-235 between N. Broadway and Hydraulic soon.

Advertisement

A third part of the project will be on East Kellogg from Washington to Hillside. The entire project could be complete by mid-August at a cost of $3.1 million.